Event

Beaver Island receives a bid for King's Highway repaving

Also Beaver Island King's Highway repaving bid 2014 · Beaver Island road paving 2014

Draft — sources verified, prose evolving

Locator map: Beaver Island highlighted within the Beaver Island archipelago
Took place at Beaver IslandLocator plate © OpenStreetMap contributors (ODbL 1.0); depths NOAA; names USGS GNIS. How the plates are drawn.
TypeEvent
Dates2014-04-14 – 2014-11-25
WithinBeaver Island
ErasModern era
On this page
Locator map: Beaver Island highlighted within the Beaver Island archipelago
Took place at Beaver IslandLocator plate © OpenStreetMap contributors (ODbL 1.0); depths NOAA; names USGS GNIS. How the plates are drawn.
Event
Dates
2014-04-14 – 2014-11-25
Kind
Infrastructure
Where
Beaver Island
Eras
Modern era
Concepts
infrastructuretransportationgovernmentplanning
Within
Beaver Island

Summary

On April 14, 2014, bids were opened for repaving King’s Highway south from Four Corners. A forum notice identified an apparent low bidder and a bid in the range of $1.7 million; a longer thread preserved subsequent community discussion of scope, bike lanes, financing, and adjacent roads.

Evidence limits

These are contemporaneous forum reports and public discussion. They do not by themselves establish the final contract, scope, cost, or completed paving.

Sources

  1. In an election discussion, one participant said Kings Highway was scheduled to be paved the following year; another participant disputed earlier road-commission claims. The thread records local expectation and political disagreement, not an official schedule, appropriation, or contract. The later 2014 bid record provides stronger evidence that a paving project entered procurement.
    forum · www.beaverislandforum.com · 06 · t006926
  2. Community and project-related posts reported the apparent low bidder, a bid near $1.7 million, and subsequent public discussion of scope, bike lanes, financing, and related roads. The forum documents advocacy and updates, not a contract award, final scope, or completion record.
    forum · www.beaverislandforum.com · 07 · t007315
  3. Community and project-related posts reported the apparent low bidder, a bid near $1.7 million, and subsequent public discussion of scope, bike lanes, financing, and related roads. The forum documents advocacy and updates, not a contract award, final scope, or completion record.
    forum · www.beaverislandforum.com · 07 · t007353
  4. Community updates reported that paving was underway and described early asphalt work, road-edge and bicycle-safety concerns, and continued progress reporting by Beaver Island News on the Net. These observations supplement the bid-stage record but do not establish final completion or contract scope.
    forum · www.beaverislandforum.com · 07 · t007761
  5. During an election discussion, incumbent county commissioner Richard Gillespie claimed that local representation helped keep King's Highway from being deferred and said a county garage/transit/sheriff building remained planned. These are campaign-thread claims by an interested officeholder, not held county minutes or procurement records, so they do not prove causation, final timing, or facility completion.
    forum · www.beaverislandforum.com · 07 · t007803

Added 7 August 2026. Recent changes

Cite this article

Beaver Island Archive, “Beaver Island receives a bid for King's Highway repaving”, https://beaverislandarchive.org/events/beaver-island-kings-highway-repaving-bids-2014/, accessed [date], citing Beaver Island Forum, "ELECTION DAY," November 4–5, 2013. (and 3 further sources listed on the page).